Phased Spec Decomposition
Take one product + engineering spec and turn it into an ordered sequence of phases, each with its own standalone design document. The output is meant to be handed to a coding agent one phase at a time -- every document must be implementable on its own, with no unresolved questions.
North star: every phase document should leave zero design decisions for the implementer. Not "an agent probably wouldn't need to ask a question" -- an agent literally cannot make a different reasonable choice than the one the document specifies, because every choice is already made and written down.
Input
Accept a PRD, an engineering design doc, a combined spec, or rough notes that mix product intent with technical detail. If the input only covers product intent, infer a reasonable engineering approach and mark it as an assumption. If it only covers engineering, infer the product framing (who benefits, what they can now do) for each phase.
Verify Before Writing
If a codebase is available, read it before writing any engineering content. Cite what exists today with path:line, not from memory or from what the spec assumes. A phase document that describes "current state" without having read the current state is a guess, not a spec. If no codebase exists yet (greenfield), say so explicitly and proceed on the spec alone.
For each phase, note what already exists that the phase can reuse -- an existing service, table, endpoint, or library that solves part of the problem. Never let a phase rebuild something the codebase already has.
Tech Stack Choices
Brownfield (existing codebase): the stack is not a decision to make -- it's whatever Verify Before Writing found. Match the existing language, framework, database, and libraries. Introducing a new one requires a stated reason (the existing stack genuinely cannot do what this phase needs), never preference or unfamiliarity with what's there.
Greenfield (no codebase yet): Phase 1's document must pin the full stack once -- language, framework, database, hosting/deploy target, and any non-trivial third-party library -- each with a one-line rationale. Every later phase inherits this silently as a given; never re-open or re-litigate the stack in a later phase's document.
Default to boring. Prefer established, widely-used technology over novel tools unless the spec states a hard requirement only the novel choice satisfies -- name that requirement explicitly when it justifies the departure. A phased handoff is the wrong place to spend the project's appetite for risk on tooling.
A stack change mid-project is a decision, not a detail. If a later phase needs a new language, datastore, or framework the earlier phases didn't use, call it out as its own explicit decision in that phase's document: the reason, the alternative considered, and the migration cost to anything already built in the old stack.
Core Principle: Vertical Slices, Not Layers
Never phase by layer ("schema, then API, then UI" or "backend, then frontend"). A layer-based phase produces nothing a user or downstream system can exercise until every layer is done. Instead, cut vertically: each phase touches every layer it needs -- however thinly -- and ends with something that runs end to end and demonstrates real behavior.
Phase 1 is a walking skeleton: the thinnest possible path through the full system for the single most important scenario, wired for real (real network calls, real storage, real auth if auth gates the flow), not stubbed. Every phase after that adds one more increment of capability on top of a system that already works.
Example -- a URL shortener spec.
Bad (layer-based -- nothing works until phase 3):
- Phase 1: database schema for
urlsandclicks. - Phase 2: REST API for create/redirect/stats.
- Phase 3: frontend page to create and view links.
Good (vertical slices -- each phase is a working product):
- Phase 1: paste a long URL into a form, get a short code back, visiting the
short code redirects to the long URL. Real storage, no auth, no stats yet.
- Phase 2: short codes are scoped to a logged-in user's account (adds auth
end to end: login, ownership check, per-user list view).
- Phase 3: click count and last-accessed time shown on each link (adds the
clicks table, an increment-on-redirect write, and a stats row in the UI).
Every phase in the good version can be demoed to a user. None of the phases in the bad version can.
Sequencing Rules
- Phase 1 is a working skeleton. It should touch every architectural
component the final system needs, at minimal depth, for one real scenario.
- Each phase adds exactly one coherent capability. If a phase description
needs "and" to summarize it in one sentence, it is probably two phases.
- Order by dependency, not by convenience. A phase may only depend on
capabilities delivered in strictly earlier phases -- never on a phase that comes after it. When dependency order leaves a tie, do the riskiest or least-certain part first -- incremental and reversible beats big-bang; surface unknowns while there is still time to change course.
- Every phase ends in a working, demoable state. Stopping after any
phase should never leave the system half-built or non-functional.
- Fold plumbing into the phase that needs it. Do not create a
phase whose sole content is infrastructure, schema, or scaffolding with no observable behavior -- attach that work to the first phase that exercises it.
- Name cross-cutting concerns explicitly. For auth, observability,
validation, rate limiting, and error handling, state per phase whether a minimal version is enough or the full version is required, and call out which later phase upgrades it.
- Let complexity set the phase count. Do not force a round number of
phases. Count independent capabilities, integration points, and risk areas in the source spec, and let that count drive how many phases exist.
- Bound each phase's size. A phase should be implementable in roughly
1-3 focused agent sessions and land as one PR. If a phase touches more than ~8 files or introduces more than 2 new services/classes, treat that as a signal to split it further, not as a reason to write a longer doc.
- Don't design what already exists. Before specifying a new pattern,
queue, cache, or abstraction inside a phase, check whether the stack already has a built-in or established pattern for it. Reach for the existing tool before inventing a new one.
Per-Phase Design Document
Every phase gets its own complete document. A reader with zero context on the other phases must be able to implement this one from this document alone.
Product Section
- Phase goal -- one sentence: what this phase unlocks that did not exist
before.
- User story / job-to-be-done -- who benefits and what they can now do.
- In scope -- an exhaustive, explicit list of behavior this phase delivers.
- Out of scope -- what looks related but is explicitly deferred, and to
which later phase.
- Acceptance criteria -- numbered, binary, testable statements with real
numbers where relevant. "Returns 409 when the slug already exists" and "list endpoint responds in under 200ms for 10k rows" pass; "handles conflicts well" and "is performant" do not.
- UX flow -- for user-facing phases, describe the flow step by step
(screens, states, transitions) even without visual mockups.
Engineering Section
- What already exists -- code, services, or libraries this phase reuses
rather than rebuilds (see Verify Before Writing).
- Components touched -- every service, module, or repo this phase creates
or modifies.
- Data model -- schemas, fields, types, constraints, and migrations,
written out in full (as a table or code block), not summarized.
- API contracts -- every endpoint or interface added or changed: method,
path, request shape, response shape, status/error codes. Use a table or code block per endpoint.
- Key flows -- the sequence of operations for the happy path and for each
major edge case (empty input, conflict, timeout, partial failure, retry).
- Dependencies on prior phases -- the exact interfaces this phase
consumes from earlier phases; nothing implicit.
- Non-functional requirements -- only the ones this phase must actually
satisfy (latency budget, concurrency, idempotency), stated as numbers or concrete rules, not adjectives.
- File reference table -- every file this phase touches, with the change,
as a table (path:line when referencing existing logic):
| File | Change |
|---|---|
path/to/file.ts:42 | Add null check before dispatch |
- Failure modes -- for each new or changed codepath, name one realistic
way it fails in production (timeout, nil reference, race, stale data) and state whether a test covers it, whether error handling exists, and whether the failure is visible to the caller or silent. Flag any silent, untested, unhandled failure as a gap to close before the phase is done.
- Test plan -- as a table across the testing pyramid:
| Layer | What | Count |
|---|---|---|
| Unit | service.method() behavior | +N |
| Integration | cross-component flow | +N |
| E2E | user-visible journey | +N |
- Rollout -- feature flags, migration order, backward-compatibility
requirements. If the phase touches data, infrastructure, or shared state, state the rollback plan explicitly -- even "revert the PR" counts, but say it.
- Definition of done -- a checklist that maps one-to-one to the
acceptance criteria above.
Resolving Ambiguity
The source spec will have gaps. Never write "TBD," "decide later," or "up to implementer" -- a phase document with an open question is not ready to hand off. But not every gap should be closed the same way; sort each one by stakes before deciding how to close it.
Low-stakes or reversible (a default page size, a naming convention, a field's exact wording, which existing utility to call) -- make the most reasonable decision yourself, state it as an explicit assumption at the top of the affected phase document, and move on. Don't stop to ask.
High-stakes or hard-to-reverse (tech stack, data model shape that other phases build on, auth/security posture, a breaking API change, anything touching money or irreversible data loss) -- do not silently assume. Stop and ask the user before writing the affected phase document. A wrong silent guess here doesn't cost one phase, it compounds through every phase built on top of it. Name the decision, the options, and your recommendation in one short question; don't bury it inside a long draft the user has to comb through to find it.
Where a number is missing (a latency budget, a row count, a concurrency limit) and cannot be derived or safely assumed, say so explicitly and state how to measure it -- never leave it as a vague adjective.
Output Structure
- Overview -- one paragraph per phase (goal + what it unlocks), followed
by an ASCII dependency diagram across phases plus a one-paragraph sequencing rationale explaining what would break if the order changed.
- Parallelization note -- if two or more phases (or workstreams within a
phase) touch disjoint modules and share no dependency, call this out as an opportunity to hand them to separate agents/worktrees in parallel; group into lanes (Lane A: phase 2 -> phase 4 (sequential), Lane B: phase 3 (independent)). If everything is strictly sequential, say so in one line instead of forcing a diagram.
- One fully expanded design document per phase, in phase order, each
self-contained per the template above.
Where to Write Output
Default to printing the overview and all phase documents inline in the response, separated by a horizontal rule (---), unless the user asks for files on disk.
When the user asks for files (or the input itself was a file path), write them next to the source spec:
- If the source spec lives at
some/dir/spec.md, write to
some/dir/phases/phase-N-<slug>.md.
- If there is no source file (spec was pasted or described), ask the user
where to write, or default to ./phases/ in the current working directory.
- Always write an index file,
phases/README.md, containing the Overview
section (phase summaries, dependency diagram, parallelization note) with links to each phase-N-<slug>.md -- an agent or human should be able to open the index and navigate straight to the phase they're implementing.
Follow ape-style-markdown for headings, tables, and code block formatting in the output.
Handoff Readiness Checklist
Before returning the result, verify for every phase document:
- No "TBD," "later," or unresolved open question remains.
- Every high-stakes ambiguity (stack, shared data model, auth posture,
breaking changes) was resolved by asking the user, not by silent guess.
- The tech stack is either inherited from the existing codebase or pinned
explicitly in phase 1 with a rationale -- never implicit, never re-decided per phase.
- Current-state claims are backed by
path:line, not assumed from the spec. - Every data field and API shape has a concrete type, not just a name.
- Acceptance criteria are testable by inspection or automated test, not by
judgment call, and use real numbers wherever a number applies.
- Every failure mode identified has a stated test-coverage and
error-handling status -- none left as an open question.
- A rollback plan is stated for any phase touching data, infra, or shared
state.
- The phase depends only on interfaces defined in earlier phases -- check for
forward references.
- The phase's file count and new-component count fall within the sizing
bound, or the oversized phase has been split.
Final self-check. For each phase document, actually switch perspective: read it as the implementing agent would, with zero other context beyond the completed prior phases. Try to name one design decision you would still have to make. If you can name one, the document is not done -- go back and decide it. Only move on once you cannot find one.